Updates
February 19 2014
Recent Progress: Actuators Attached to the Wheelset.
February 17 2014
Recent Progress: Construction Update
December 16 2013
Recent Progress: Ballast Construction Completed
November 6 2013
Recent Progress: Rail and IWS Placement
October 24 2013
Recent Progress: Placement of Crossties
October 15 2013
Recent Progress: Ballast to Bottom of Crosstie
October 11 2013
Recent Progress: Subballast Construction (75% complete)
October 4 2013
Recent Progress: Subgrade Construction Complete
September 23 2013
Recent Progress: Subgrade Construction (~50% complete)
September 17 2013
Recent Progress: Completed Walls and Bulkheads
August 15 2013
Recent Progress: Completed Walls and Bulkheads
July 25 2013
Recent Progress: Vertical Columns
July 23 2013
Recent Progress: Floor Installed and Columns Extended
July 18 2013
Recent Progress: Floor Beams Completed and Laid out for Construction